The Map Ta Phut Industrial Port Phase 3 Project is an important development

to enhance Thailand’s infrastructure capacity.

It increases the efficiency and safety of liquid cargo, natural gas, and petrochemical transportation to meet future demand.
The project supports target industries within the Eastern Economic Corridor (EEC), especially advanced petrochemicals and clean energy,
while promoting energy security, environmental sustainability, and international safety standards.

Current Capacity of
Map Ta Phut Industrial Port

Map Ta Phut Industrial Port is the largest industrial port in Thailand. It has the capacity to transport natural gas and other products with a total volume of 16 million tonnes per year. Currently, there are 12 operators, 9 of whom are specialized port operators and 3 of which are public port operators.

Overview of the Map Ta Phut Industrial Port Development Project Phase 3

Project location: Map Ta Phut Subdistrict, Mueang Rayong District, Rayong Province

Project owner: Industrial Estate Authority of Thailand (IEAT)

Objectives:

Scope of the Project: Infrastructure work (dredging and reclamation)

Map Ta Phut Industrial Port Development Project Phase 3

Stage 1

Private partner: Gulf MTP LNG Terminal Co., Ltd. (GMTP)

Contract signing date: 1 October 2019

Capacity: Gas terminal operations with an annual capacity of 11 million tonnes

Project area: Plot B, 200 rai; navigation channel depth 16 meters; pier length 1,415 meters; 3 gas terminals and 4 service wharfs

Concession period: 35 years for the private sector (3 years for infrastructure construction, 2 years for gas terminal construction, and 30 years for operations)

Responsibilities of the Industrial Estate Authority of Thailand (IEAT)

Responsibilities of the private partner (GMTP):

Project Implementation Plan

IEAT signed the contract with GMTP.

1 October 2019

Project commencement for infrastructure construction (NTP 1)

28 December 2021

Completion of marine construction

30 March 2025

Start of gas terminal construction by late 2025

15 October 2025

Start of gas terminal construction by GMTP

Gas terminal operations scheduled to begin

in 2029

Construction of the Map Ta Phut Industrial Port Development Project
Phase 3, Stage 1, was completed on 31 March 2025.

Dredging and reclamation

Revetment